给我解释一下做这道题---**Diagram Description:**
* **Type:** Network diagram, representing a project schedule. This appears to be a Critical Path Method (CPM) or PERT chart.
* **Main Elements:** The diagram consists of several nodes (boxes) representing tasks and directed edges (arrows) representing dependencies between tasks.
* **Task Nodes:** Each task is represented by a box divided into sections. The sections are labeled:
* Top Left: ES (Early Start)
* Top Right: EF (Early Finish)
* Bottom Left: LS (Late Start)
* Bottom Right: LF (Late Finish)
* Center: Duration and Task Name.
* **Tasks and Durations:**
* Task A: Duration = 4
* Task B: Duration = 6
* Task C: Duration = 7
* Task D: Duration = 5
* Task E: Duration = 8
* Task F: Duration = 8
* Task G: Duration = 3
* **Dependencies (Arrows):**
* An implicit start node connects to Task A.
* Task A connects to Task B and Task E.
* Task B connects to Task C.
* Task C connects to Task D.
* Task D connects to Task G.
* Task E connects to Task F.
* Task F connects to Task G.
* **Given Values in Diagram:**
* Task A has an initial ES value of 0.
**Questions:**
1. 确定所有任务的ES, EF, LS, LF
* *English Translation:* Determine the ES, EF, LS, and LF for all tasks.
2. 确定关键路径以及关键路径的长度?
* *English Translation:* Determine the critical path and the length of the critical path?
3. 确定F的自由浮动和总浮动?
* *English Translation:* Determine the free float and total float for F?